EXISTING RESTROOM FACILITIES & HALLWAY UPDATE TIMELINE
AUGUST 26
NEW LED LIGHT FIXTURES INSTALLED

SEPTEMBER 8
MOULDING & TRIM PAINTED AROUND HALLWAY RESTROOM TO MATCH REST
OF HALLWAY


SEPTEMBER 10
ADA RAMP ENTRANCE PRIMED FOR PAINTING

SEPTEMBER 11
FIRST COAT OF PAINT ON ADA RAMP ENTRANCE

SEPTEMBER 12 - 14
SECOND & THIRD COATS ON ADA RAMP ENTRANCE
SECOND COAT ON HALLWAY RESTROOM MOULDING & TRIM
FRESH COAT OF PAINT IN HALLWAY & STAIRWELL TO COVER SCUFFS




SEPTEMBER 16 & 17
PAINTING EXTISTING RESTROOMS


SEPTEMBER 18 - 20
FRESH COAT OF PAINT ON BANISTER DOWN TO BASEMENT
CLEAN DUST AND COBWEBS FROM STAIRWELL


SEPTEMBER 21
NEW FLOORING INSTALLED



SEPTEMBER 22
NEW TOILETS INSTALLED


PROJECT COMPLETE!