ADA ACCESSIBLE RESTROOM CONSTRUCTION TIMELINE
JULY 30
CONSTRUCTION BEGINS

AUGUST 11
NEW DRYWALL INSTALLED
UPDATED ELECTRICALS

AUGUST 2
OLD FLOOR TILES REMOVED
NEW PLUMBING INSTALLED

AUGUST 18
CREATED STORGE CLOSET ON OPPOSITE WALL

AUGUST 23

SEPTEMBER 1


SEPTEMBER 6
PAINTING COMPLETE

SEPTEMBER 21
NEW FLOORING INSTALLED

SEPTEMBER 22
TOILET & SINK INSTALLED


SEPTEMBER 27
FINAL INSPECTION
PROJECT
COMPLETE!